| Pumping Station, Alderman Road |
September 8, 1998 |
November 12, 1998 |
| Child Care Center |
February 25, 1999 |
March 11, 1999 |
| Gilmer Hall Greenhouse Expansion |
April 5, 1999 |
June 23, 1999 |
| Special Collections Library |
September 21, 1999 |
November 23, 1999 |
| Clark Hall Additions |
October 8, 1999 |
December 9, 1999 |
| Stone Hall Additions |
December 28, 1999 |
February 17, 2000 |
| Coastal Research Center Oyster |
January 30, 2000 |
March 30, 2000 |
| O-Hill Dining Hall Expansion |
March 23, 2000 |
May 26, 2000 |
| Miller Center Addition and Renovation |
February 28, 2000 |
April 27, 2000 |
| Lake (Wise) |
October 17, 2000 |
December 1, 2000 |
| Central Grounds Chilled Water Plant |
May 16, 2000 |
July 13, 2000 |
| Campbell Hall Chiller Replacement |
May 16, 2000 |
July 13, 2000 |
| Fayerweather Renovations |
July 7, 2000 |
September 5, 2000 |
| Newcomb Hall Chiller Addition |
May 15, 2000 |
not needed |
| Monroe House Student Residence |
November 7, 2000 |
December 11, 2000 |
| Chilled Water Line - McCormick Rd |
March 22, 2001 |
May 15, 2001 |
| Water Line - McCormick Residences |
April 10, 2001 |
May 16, 2001 |
| Law School, Student Faculty Center |
April 10, 2001 |
June 5, 2001 |
| Hospital Addition |
April 10, 2001 |
June 8, 2002 |
| Aquatic and Fitness Center Addition |
April 12, 2001 |
pervious EIR applies |
| Material Sciences Building |
August 30, 2001 |
October 7, 2001 |
| Multistory Storm Water Improvements |
June 6, 2001 |
August 6, 2001 |
| Grounds Walk Bridge |
August 8, 2001 |
October 9, 2001 |
| Parking Garage (Emmet and Ivy Road) |
November 29, 2001 |
September 4, 2002 |
| Studio Art Building and Commons |
March 21, 2002 |
May 29, 2002 |
| Campbell Hall Additions |
March 21, 2002 |
May 29, 2002 |
| Basketball Arena |
May 7, 2002 |
April 4, 2003 |
| O-Hill Dining (new facility) |
August 8, 2002 |
October 18, 2002 |
| Temp. Classrooms HSC |
July 19, 2002 |
September 23, 2002 |
| MRI Addition |
July 25, 2002 |
September 20, 2002 |
| ECC Radio Towers |
September 27, 2002 |
November 22, 2002 |
| AFC Chiller Plant |
October 25, 2002 |
December 13, 2002 |
| Ruffner-Physics Parking Lot |
October 25, 2002 |
December 13, 2002 |
| South Parking Garage Addition |
February 19, 2003 |
August 8, 2003 |
| Cobb Hall Emergency Generator |
May 22, 2003 |
July 5, 2003 |
| Swing Space Buildings - Ruffner |
June 3, 2003 |
August 8, 2003 |
| Chilled Water Lines Arts Precinct |
July 16, 2003 |
September 23, 2003 |
| MR4 Modular Units - Vivaria |
September 2, 2003 |
October 22, 2003 |
| Cavalier Substation Expansion |
December 11, 2003 |
February 4, 2004 |
| Varsity Hall Relocation |
February 18, 2004 |
March 25, 2004 |
| Rouss Hall Renovation and Addition |
February 27, 2004 |
April 26, 2004 |
| Cocke Hall |
March 8, 2004 |
May 18, 2004 |
| New Residence Hall Wise College |
April 2, 2004 |
May 18, 2004 |
| Central Grounds Water Line |
April 2, 2004 |
June 11, 2004 |
| Main Heat Plant Upgrade |
October 5, 2004 |
December 10, 2004 |
| UVA Recycling Center |
May 18, 2004 |
July 6, 2004 |
| JAG Security Upgrade & Parking Lot Expansion |
June 9, 2004 |
July 23, 2004 |
| University Avenue Lighting |
July 6, 2004 |
September 14, 2004 |
| Interim Sports Medicine |
August 3, 2004 |
September 16, 2004 |
| Maury Hall Pedestrian Link |
July 7, 2004 |
October 21, 2004 |
| Campbell Hall Chiller Plant |
July 8, 2004 |
September 2, 2004 |
| Darden Plaza (Wise) |
July 23, 2004 |
September 14, 2004 |
| Artificial Turf Field Carr's Hill |
September 14, 2004 |
November 16, 2004 |
| Varsity Hall Relocation (second location) |
November 2, 2004 |
January 4, 2005 |
| Lower Grass Practice Turf Field |
June 17, 2005 |
August 1, 2005 |
| Madison Bowl Improvements |
June 22, 2005 |
August 1, 2005 |
| Emmet Street Lighting |
August 9, 2005 |
October 17, 2005 |
| Nursing School Expansion |
October 4, 2005 |
12/8/2005 |
| Carr's Hill Support Facility |
November 7, 2005 |
December 19, 2005 |
| Practice Football Turf Field |
Feburary 3, 2006 |
April 3, 2006 |
| Arts Grounds Parking Garage |
June 8, 2006 |
July 31, 2006 |
| South Lawn Project, Phase I |
August 18, 2006 |
October 25, 2006 |
| Blandy Farm Water Line Replacement |
August 28, 2006 |
October 27, 2006 |
| Physics Waterline Replacement |
August 28, 2006 |
October 19, 2006 |
| Wise - Chancellor's Residence |
October 9, 2006 |
December 13, 2006 |
| O-Hill Residence Hall |
October 17, 2006 |
December 22, 2006 |
| Medical Education Building |
October 24, 2006 |
December 6, 2006 |
| Wise- Crockett Hall and Main Entrance |
November 28, 2006 |
January 23, 2007 |
| Wise - Drama and Arts Center |
December 11, 2006 |
January 26, 2007 |
| Hereford Connector Road |
January 10, 2007 |
February 2, 2007 |
| Bavaro Hall |
March 6, 2007 |
May 7, 2007 |
| South Chiller Plant Expansion |
March 19, 2007 |
May 21, 2007 |
| Scott Monument |
March 26, 2007 |
May 7, 2007 |
| East Range Sewer Line Replacement |
April 16, 2007 |
June 18, 2007 |
| Wise - Science Building Renovation |
July 27, 2007 |
October 1, 2007 |
| Hospital Bed Expansion |
August 13, 2007 |
October 11, 2007 |
| Emily Couric Cancer Center |
August 24, 2007 |
October 24, 2007 |
| PCS Addition, ITC Data Center |
September 20, 2007 |
November 28, 2007 |
| Wise - Dining and Residence Hall |
October 4, 2007 |
December 4, 2007 |
| Wise - Smiddy and IT Building |
January 28, 2008 |
March 25, 2008 |
| Southwest Virginia Higher Eduation Center |
January 28, 2008 |
March 26, 2008 |
| The Park - Turf Field Conversion |
February 20, 2008 |
in process |
| |
|
|
Click here for a printable list
Click on the name of the EIR to view the EIR, if available
Click on the date of the EIR to read the Governor's Approval and DEQ comments, if available |
|
|